The planning exemptions Ireland brought into force on 27 July 2026 let homeowners in the Republic of Ireland build a rear extension of up to 45 square metres, a side or rear dormer, a garden structure of up to 30 square metres and, for the first time, a detached home of 32 to 45 square metres in the back garden, all without planning permission. Each exemption has conditions on size, height, distance from boundaries and open space, the garden home and house subdivision exemptions end on 31 December 2030, and Building Regulations still apply to every project.

New planning exemptions for houses came into force in the Republic of Ireland on 27 July 2026, through seven sets of regulations signed on 16 July 2026. They raise the extension limit from 40 to 45 square metres and add new exemptions for dormers, front roof lights, external wall insulation, house subdivision and a detached home in the back garden.

What changed in the planning exemptions Ireland introduced in July 2026

Under the planning exemptions Ireland uses, exempted development is building work that does not need planning permission because it meets conditions set out in the Planning and Development Regulations 2001. The Department of Housing, Local Government and Heritage described the July 2026 package as the first substantial update to these rules in almost 25 years, following a public consultation that drew close to 1,000 submissions.

The changes are spread across seven statutory instruments, numbered S.I. 338 to S.I. 344 of 2026. The table sets out each change and the key limit, and the sections that follow explain the conditions.

WorksWhat the July 2026 rules allowKey limit
Rear extensionLarger exemption than before45 square metres in total
Shed, garage, home office or gymLarger exemption than before30 square metres in total
Detached garden homeNew exemption32 to 45 square metres
Subdividing the houseNew exemptionTwo units, each at least 32 square metres
Side or rear dormerNew exemption30 cubic metres of internal volume
Front roof lightsNew exemptionTwo, each up to 100 by 90 centimetres
External wall insulationNew exemption150 millimetres thick
Heat pumpFront of house now allowed2.5 square metres in total
Bicycle or bin storeNew exemption3.5 square metres, 1.4 metres high

These planning exemptions Ireland adopted apply to houses in the Republic of Ireland only. Our existing guide, planning permission explained simply, covers how a full planning application works when a project falls outside the exemptions.

The 45 square metre extension exemption

The headline change in the planning exemptions Ireland adopted this year is to Class 1, which covers extensions to the rear of a house. S.I. 338 of 2026 raises the limit from 40 to 45 square metres, and the same instrument governs converting an attached garage, store or shed into part of the house.

Earlier extensions count towards the limit

The 45 square metres is a total, not a fresh allowance. If the house has been extended since 1 October 1964, including extensions built with planning permission, those earlier extensions are added to the new one, and the combined floor area cannot go above 45 square metres. A house that already has a 30 square metre kitchen extension, for example, has 15 square metres left under the exemption.

Upstairs extensions have tighter limits

Any part of the extension above ground level is capped at 12 square metres on a terraced or semi detached house and 20 square metres on a detached house, again counting earlier extensions. Above ground floor extensions must be at least 2 metres from any party boundary. The walls cannot be higher than the rear wall of the house, and the roof cannot be used as a balcony or terrace.

Garden space and windows

The extension must leave at least 25 square metres of private open space within the grounds of the house. Before July 2026 this was measured at the rear only, but the amended wording now counts all private open space around the house. Ground floor windows must be at least 1 metre from the boundary they face, and windows above ground level must be at least 8 metres from the boundary they face, reduced from 11 metres under the old rules.

Sheds, garages and garden rooms up to 30 square metres

Class 3 covers sheds, stores, garages, greenhouses and similar structures in the grounds of a house, and the Department’s announcement listed home offices and gyms among them. The total area of all such structures has risen from 25 to 30 square metres. None of them can be built forward of the front wall of the house, and together they must leave at least 25 square metres of private open space to the rear or side.

The height limit is 4 metres for a building with a tiled or slated pitched roof and 3 metres for any other roof. A structure under Class 3 cannot be used as living accommodation and must be used only for purposes connected with enjoying the house. Anyone who wants a garden building to sleep in needs the separate garden home exemption.

Detached garden homes without planning permission

Of all the planning exemptions Ireland has added, the most significant is Class 3A, introduced by S.I. 340 of 2026. It allows a detached home in the rear garden of a house, which the Department called an auxiliary habitable dwelling, without a planning application.

Size, height and position

The garden home must have a floor area between 32 and 45 square metres, and the regulations count it together with any existing sheds or garden structures when measuring that limit. Its height cannot exceed 4 metres with a tiled or slated pitched roof, or 3 metres otherwise. It must be at least 0.6 metres from any wall or party boundary, and at least 25 square metres of private open space must remain for the main house.

Who can live there and how it connects

The garden home can only be occupied together with the main house and cannot be sold or subdivided separately. It cannot be used for short term letting, and the owner must be living in the main house as their sole or main residence when the works begin. It cannot have its own water, wastewater or other utility connections, so it shares the services of the main house. Caravans and mobile homes do not qualify, and no new vehicle or pedestrian entrance onto a road is allowed.

Notifying the council

Before work starts, the owner must notify the local planning authority at least 14 days in advance, giving the location and Eircode. The exemption covers only garden homes started and finished by 31 December 2030. Houses with septic tanks face extra conditions, including keeping the garden home off the approved percolation area and confirming the treatment system has enough capacity.

Subdividing a house into two homes

Class 1A, introduced by S.I. 339 of 2026, allows a house to be divided into no more than two self contained units within its existing walls. Each unit must have at least 32 square metres of floor space and must not rely on shared internal space other than for access.

This exemption cannot be combined with a garden home on the same property, so owners need to choose one route or the other. Like the garden home, it requires 14 days’ notice to the planning authority and covers only works completed by 31 December 2030. Our guide to small spaces that work harder has ideas for planning compact rooms in a smaller unit.

Attic conversions, dormers and roof lights

Before the July 2026 planning exemptions Ireland introduced, a dormer window generally needed planning permission. S.I. 344 of 2026 created two new exemptions for roof works on a house.

Side and rear dormers

Class 1B allows a dormer roof extension and dormer window to the side or rear of the house. The internal volume of the dormer, together with any other dormers on the house, cannot exceed 30 cubic metres. The dormer cannot rise above the ridge of the roof and must be set back at least 20 centimetres from the eaves. Front dormers are not covered, so they still need planning permission.

Roof lights on the front roof

Class 1C allows up to two roof lights on the existing front roof plane of the house. Each roof light can measure no more than 100 centimetres in length and 90 centimetres in width. An attic conversion that uses these exemptions must still meet the Building Regulations on fire safety, stairs, ventilation and head height before the attic can be used as a habitable room.

External insulation, heat pumps and other smaller works

Several smaller exemptions came in at the same time, and they matter to anyone planning an energy upgrade. These planning exemptions Ireland introduced alongside the larger changes remove the need for permission for some of the most common retrofit works.

External wall insulation

Class 63 allows external wall insulation on the front, rear or gable walls of a house, up to 150 millimetres thick. It cannot encroach onto a public road and must not materially change the appearance of the house in a way that is out of character with the house and its neighbours. The Department said this exemption lines up with the existing SEAI grant rules for external insulation.

Heat pumps at the front of a house

Air source and ground source heat pumps were already exempt, but they could not be placed on or forward of the front wall or roof. S.I. 342 of 2026 removed that restriction, so a heat pump can now go at the front as long as it does not encroach onto a public road. The other conditions stay in place, including a total area of 2.5 square metres and a noise limit measured at the nearest neighbouring home.

Bicycle and bin stores

Class 62 allows a bicycle or bin store of up to 3.5 square metres and 1.4 metres high. A store at the front must be set back 0.6 metres from the front wall of the house and must not cut the open space in the front garden by more than 50%.

When the planning exemptions in Ireland do not apply

The planning exemptions Ireland offers only apply if every condition is met. A project that goes over a single limit, such as an extension of 46 square metres, needs full planning permission for the whole project, not just the extra metre.

The regulations also contain general restrictions that can remove an exemption altogether. These commonly affect protected structures, homes in architectural conservation areas, and houses where a condition in an earlier planning permission limits future development. Check the planning history of your house with the local council before you start, especially if the house was built under a permission with conditions attached.

Exemption from planning permission is not exemption from the Building Regulations. Every project in this guide still has to comply with the Building Regulations, including fire safety, and the Department has said it will review the exemptions 18 months after they came into operation.

Questions about planning exemptions

Can I get written confirmation that my project is exempt?

You can apply to your local council for a Section 5 declaration, which is a formal decision on whether a specific project is exempted development. A fee applies, and the decision can be referred to An Coimisiún Pleanála if you disagree with it. Many solicitors ask for this confirmation when a house is later sold.

Do these exemptions apply to apartments?

The classes in this guide apply to houses. Apartment owners usually need planning permission for external changes, and any works also need the agreement of the management company under the lease.

Can I remove a chimney without planning permission?

S.I. 343 of 2026 introduced an exemption for removing a chimney from a house, as long as it is not part of a stack shared with a neighbouring home. The roof must be finished to match the existing roof, and the work must respect wildlife law protecting nesting birds and bats.

Do the same rules apply in Northern Ireland?

These exemptions apply only in the Republic of Ireland. Northern Ireland and England have their own permitted development rules with different limits, and homeowners there should check with their local council before starting work.

Planning your project under the new exemptions

Measure your existing extensions, sheds and garden space before you design anything, because those figures decide how much of each allowance is left. Ask the council for the planning history of the house, and talk to an architect or engineer about Building Regulations compliance before you appoint a builder.